Question: The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:
Activity Immediate Predecessor Time (Weeks)
| A | ----------- | 3 |
| B | A | 2 |
| C | A | 4 |
| D | A | 4 |
| E | B | 6 |
| F | C,D | 6 |
| G | D,F | 2 |
| H | D | 3 |
| I | E,G,H | 3 |
- Draw the network diagram.
- What is the critical path?
- Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten?
- What is the new critical path and earliest completion time?