(See Steps) A project that needs to be done involves the eight tasks A, B, C, D, E, F, G, and H with the following sequencing requirements and task durations:
Question: A project that needs to be done involves the eight tasks A, B, C, D, E, F, G, and H with the following sequencing requirements and task durations:
| Task | Immediate predecessor(s) | Task duration in weeks |
| A | — | 2 |
| B | — | 6 |
| C | A | 4 |
| D | A, B | 1 |
| E | B, C | 4 |
| F | E | 2 |
| G | C, E | 5 |
| H | D, G | 3 |
- Draw the corresponding project network.
- What is the minimum amount of time the project will take, and which path(s) would be critical for meeting that timeframe?
- Which of the activities would have the most slack time available?