(Solution Library) A PERT chart includes the following information: Activity Immediate Predecessor T/o T/m T/p A NONE 3 6 10 B A 4 9 14 C B AND A 1 4 8 D B
Question: A PERT chart includes the following information:
| Activity | Immediate Predecessor | T/o | T/m | T/p |
| A | NONE | 3 | 6 | 10 |
| B | A | 4 | 9 | 14 |
| C | B AND A | 1 | 4 | 8 |
| D | B AND C | 5 | 7 | 10 |
| E | C | 2 | 5 | 8 |
| F | D AND E | 2 | 5 | 9 |
- Draw a network and label each activity with is expected time and variance.
- Calculate the expected completion time of the project.
- What is the probability that the project will be completed in 30 days?
- Are the PERT assumptions used to calculate the probability in part "C" realistic in this case? Why or why not?
- What is the effect of the large variance in activity B?