A manager intends to order a new machine and must now decide on the number of spare parts to order along with the machine. The parts cost $350 each and have no salvage value. If the manager does not have a spare part on hand it costs $650 in lost production. The manager has compiled a frequency distribution for the probable usage of spare parts, as shown. How many spare parts should the manager order?

No. of Spares Frequency
0 .08
1 .30
2 .24
3 .20
4 .18