[Steps Shown] A machine set to fill a bottle with 60 grams of liquid was started at 7 a.m. today. Slight variations (called chance variations) were expected.
Question: A machine set to fill a bottle with 60 grams of liquid was started at 7 a.m. today. Slight variations (called chance variations) were expected. The quality control inspector made her initial check of the weights at 8 a.m. She selected five bottles from the first hour of production and weighed the contents of each bottle. The results of the first seven inspections are shown below.
Time 1 2 3 4 5
8 am 60 59 60 60 60
9 am 60 60 60 60 60
10 am 60 60 60 59 60
11 am 60 59 60 60 60
12 pm 60 60 59 60 59
1 pm 60 60 59 60 59
2 pm 60 59 59 59 59
- Develop a control chart for the sample means. What are the limits? What is the grand mean? Comment on this chart.
- Develop a control chart for the sample ranges. What are the limits? What is the mean range? Comment on this chart.
- As the Quality Control Inspector, what would you report to the plant manager?