[Step-by-Step] Hamilton county parks is planning to develop a new park and recreational area on a recently purchased 100 acre tract. Project development activities
Question: Hamilton county parks is planning to develop a new park and recreational area on a recently purchased 100 acre tract. Project development activities include clearing playground and picnic areas, constructing roads, constructing a shelter house, purchasing picnic equipment, and so on. The following network and activity times (in weeks) are being used in the planning, scheduling, and controlling of this project.
H
D
A
FINISH
I
E
C
START
G
F
B
| ACTIVITY | A | B | C | D | E | F | G | H | I |
| TIME | 9 | 6 | 6 | 3 | 0 | 3 | 2 | 6 | 3 |
- What is the critical path for this network?
- Show the activity schedule for the project
- The park commissioner would like to open the park to the public within 6 months from the time the work on the project is started. Does this opening date appear to be feasible? Explain.