(All Steps) Given the following network with activities and times estimated in days, Activity Optimistic Most Probable Pessimistic A 2 5 6 B 1 3 7 C 6 7
Question: Given the following network with activities and times estimated in days,
| Activity | Optimistic |
Most
Probable |
Pessimistic |
| A | 2 | 5 | 6 |
| B | 1 | 3 | 7 |
| C | 6 | 7 | 10 |
| D | 5 | 12 | 14 |
| E | 3 | 4 | 5 |
| F | 8 | 9 | 12 |
| G | 4 | 6 | 8 |
| H | 3 | 6 | 8 |
| I | 5 | 7 | 12 |
| J | 12 | 13 | 14 |
| K | 1 | 3 | 4 |
| a. | Please fill in all numbers in boxes ES, EF, LS, and LF then determine the critical path activities. |
| b. | What is the expected time to complete the project? |
| c. | What is the probability the project will take more than 28 days to complete? |