[Solution Library] The following represents a project with known activity times. All times are in weeks. Activity Immediate Predecessor Time A - 4 B - 3 C A 2 D B
Question: The following represents a project with known activity times. All times are in weeks.
| Activity | Immediate Predecessor | Time |
| A | - | 4 |
| B | - | 3 |
| C | A | 2 |
| D | B | 7 |
| E | C, D | 4 |
| F | B | 5 |
- What is the minimum possible time required for completing the project?
- What is the latest possible time that Activity C may be started without delaying the completion of the project?
- What is the slack time for Activity D?
- What is the latest finish time for Activity E?