Question: The following represents a project with known activity times. All times are in weeks.

Activity Immediate Predecessor Time
A - 4
B - 3
C A 2
D B 7
E C, D 4
F B 5
  1. What is the minimum possible time required for completing the project?
  2. What is the latest possible time that Activity C may be started without delaying the completion of the project?
  3. What is the slack time for Activity D?
  4. What is the latest finish time for Activity E?