[All Steps] The following information is provided to construct a project network and a project crash data: Activity time(weeks) Activity Cost ($) Activity
Question: The following information is provided to construct a project network and a project crash data:
Activity time(weeks) Activity Cost ($)
Activity (i,j) Activity predecessor Normal Crash Normal Crash
A (1,2) ---------------------- 16 8 2,000 4,400
B (1,3) ---------------------- 14 9 1,000 1,800
C (2,4) A 8 6 500 700
D (2,5) A 5 4 600 1,300
E (3,5) B 4 2 1,500 3,000
F (3,6) B 6 4 800 1,600
G (4,6) C 10 7 3,000 4,500
H (5,6) D,E 15 10 5,000 8,000
Required:
- Construct the project network
- Manually crash the network to 28 weeks.
Deliverable: Word Document 