[All Steps] The following information is provided to construct a project network and a project crash data: Activity time(weeks) Activity Cost ($) Activity


Question: The following information is provided to construct a project network and a project crash data:

Activity time(weeks)                Activity Cost ($)

Activity     (i,j)       Activity predecessor           Normal              Crash                   Normal         Crash

A                (1,2)       ----------------------                    16                     8                           2,000             4,400

B                 (1,3)      ----------------------                     14                     9                           1,000             1,800

C                 (2,4)             A                                                8                       6                                 500             700

D                (2,5)              A                                                5                       4                                600             1,300

E                 (3,5)              B                                                4                       2                            1,500              3,000

F                 (3,6)              B                                                 6                      4                                 800              1,600

G                (4,6)              C                                                 10                    7                             3,000              4,500

H                 (5,6)              D,E                                             15                   10                           5,000               8,000

Required:

  1. Construct the project network
  2. Manually crash the network to 28 weeks.

Price: $2.99
Solution: The downloadable solution consists of 3 pages
Deliverable: Word Document

log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in