[Steps Shown] Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and
Question: Davison Construction Company is building a luxury lakefront home in the Finger Lakes region of New York. Coordination of the architect and subcontractors will require a major effort to meet the 44-week (approximately 10-month) completion date requested by the owner. The Davison project manager prepared the following project network:
Estimates of the optimistic, most probable, and pessimistic times (in weeks) for the activities are as follows:
- Find the critical path.
- What is the expected project completion time?
- What is the probability the project can be completed in the 44 weeks as requested by the owner? d. What is the probability the building project could run more than 3 months late? Use 57 weeks for this calculation.
e. What should the construction company tell the owner?
Deliverable: Word Document 