Question: A competitor of Kozar International, Inc. has begun marketing a new instant-developing film project. Kozar has had a similar product under study in its R\&D department but has not yet been able to begin production. Because of the competitor's action, top managers have asked for a speedup of R&D activities so that Kozar can produce and market instant film at the earliest possible date. The predecessor information and activity time estimates in months are shown in the next column.
- Draw the project network.
- Develop an activity schedule for this project using early and late start and finish times, compute activity slack time, and define the critical activities.
- What is the probability the project will be completed in time for Kozar to begin marketing the new product within 27 months?