Question: Assume that the previous project has the following activity times (in months).

Activity A B C D E F G
Time 4 6 2 6 3 3 5

A.) Find the critical path

B.) The project must be completed in 1 ½ years. Do you anticipate difficulty in meeting the deadline? Explain.

(previous problem information is below the project is complete when activities F and G are both complete).

Activity A B C D E F G
Immediate Predecessor ----- ----- A A C,B C,B D,E