[Steps Shown] Assume that you are the manager of Assembly, Inc. You have just received an order for 40 units of an industrial robot, which is to be delivered
Question: (40 points)
Assume that you are the manager of Assembly, Inc. You have just received an order for 40 units of an industrial robot, which is to be delivered at the start of week 7 of your schedule. Using the following information, determine how many units of subassembly C to order and the timing of those orders (using MRP method). Assume that subassembly C must be assembled in multiples of 30 units. Also assume that an extra 30 percent scrap for Robot assembly must be included.
| Item | Lead Time (weeks) | On hand |
Component
B, G, C(3) |
| Robot | 2 | 20 | |
| B | 1 | 5 | E, F |
| C | 1 | 10 | G(2), 11 |
| E | 2 | 4 | - |
| F | 1 | 8 | - |
| G | 2 | 18 | - |
| H | 2 | 10 | - |
Deliverable: Word Document 