[Answer] The Department of the Interior has named the Saratoga - #80087


SARATOGA MOUNTAIN NATIONAL PARK CASE

The Department of the Interior has named the Saratoga Mountain area a national park. It is in the planning stages of developing a campsite area over 500 acres of currently undeveloped land. This campsite will span the extremities of the park, from the proposed Mission Creek Campsite area in the west to the Wild Coyote Campsite area in the east.

At this time all the contracts for this project have been awarded with exception of

selecting the company that will develop the management information system (MIS) for Saratoga National Park. The three bidders for this contract are (1) QM Associates, (2) MS Infostructures, and (3) the SBAE Company.

The project has been subdivided into 10 individual activities, as depicted in the

PERT/CPM network in Figure 1. Activity J is the MIS task.

PERT

Based on similar projects, it has been possible to determine a cost/time correspondence between the various activities of the project. The normal and crash costs and times (in weeks) are given in the following table.

PERT

Activity F that will be performed by Ellis Electric involves laying electrical cable for the

project. To minimize its cost, Ellis will design the system to use the least amount of

electrical cable.

Ellis Electric will charge the government an amount between $100,000 and $200,000. For $100,000, Ellis Electric can assign enough workers to lay 300 feet of cable per week. For $200,000, Ellis will assign additional workers to lay 500 feet of cable each week.

Activity 1 involves constructing one (narrow) paved two-lane road from Mission Creek in the west to Wild Coyote in the east. This work will be done by Harriman Construction.

To minimize costs, the department will pay Harriman to build the road of minimum

distance between the two campsites. At a cost to the governments of $25,000 per week, 200 feet of roadway can be completed in a week. If the cost is increased to $36,000 per week, the completion rate will increase to 250 feet per week.

Due to heavy brush and mountainous nature of the area, 12 possible dirt paths exist

between the campsites. Neither Ellis Electric nor Harrison Construction is permitted to clear out additional areas for constructing either underground cable or the paved road. Thus, electrical cable must be laid and the road must be built along areas of the dirt paths. Figure 2 is a map of the possible dirt paths between campsites showing distances in feet.

Each of the three companies competing for the MIS task ha been asked to submit a

minimal cost and a minimal time (in weeks) bid. The bids are summarized in the

following tale.

PERT

The "grand opening" of Saratoga National Park had been scheduled for exactly 52 weeks from now. It is imperative that the project be completed within the 52-week period because a delay of even one day in the opening of the park would result in revised travel costs for the dignitaries, lost income to the park, and other expenses.

Based on the given time and cost estimates, prepare a memo to the Department of the

Interior giving the costs and scheduling for each activity so that the project will be

completed within 52 weeks at a minimum total costs.. Be sure to emphasize the

assumptions you made to perform your analysis. Also include the following

recommendations:

· The firm to be awarded the MIS contract and its funding level;

· The layout and funding for the Ellis Electric cable-laying activity

· The design and funding for the Harriman Construction paved road

· activity.

PERT

MEMORANDUM:

Your memorandum should be professional in style. Of course, it is typed! Your

supporting work (e.g. formulation and computer solution) should be placed in separate appendices and only the results cited in your memo. The paper will be evaluated according to (1) Composition (grammar, sentence and paragraph construction, transition sand coherence); (2) Mechanics (typing, spelling, punctuation, and format; (3) Content (substance - each question sufficiently addressed); (4) Reflection (analysis).

More information concerning the writing of a memo will be forthcoming. You are

encouraged to work in teams; however the team size is limited to 3. Team members will be asked to evaluate each other's participation. Remember, this is worth 15% of your grade.

Price: $92.95
Solution: The downloadable solution consists of 23 pages, and 1284 words
Deliverable: Word Document and pdf





log in to your account

Don't have a membership account?
REGISTER

reset password

Back to
log in

sign up

Back to
log in