[Solution Library] points The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and
Question: 24 points
The following jobs are waiting to be processed at Rick Carlson’s machine center. Carlson’s machine center has a relatively long backlog and sets fresh schedules every 2 weeks, which do not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241. At this time, no other jobs are in process or waiting to be worked.
| Job | Date Job Received | Production Days Needed | Date Job Due |
| A | 5 | 28 | 35 |
| B | 9 | 12 | 70 |
| C | 10 | 36 | 51 |
| D | 12 | 45 | 62 |
| E | 17 | 18 | 89 |
- For the following 3 sequencing rules, compute the average flow time from today (consider that today, which is day 241, is day 1 for determining flow time), average days late (with no credit for being early) and average days early (with zero days early for a job that is late). The rules are the following:
- FCFS (First Come First Served)
- EDD (Earliest Due Date)
- SPT ( Shortest Processing Time)
- CR (Critical Ratio)
b) Which rule would you recommend using? Why?
Deliverable: Word Document 