(All Steps) 3 (page 9 0 in the text) Draw the activity on node (AON) project network associated with the following activities for Dave Carharts consulting
Question: Problem 3. 3 (page 9 0 in the text)
- Draw the activity on node (AON) project network associated with the following activities for Dave Carharts consulting company project. How long should it take Dave and his team to complete this project? What are the critical path activities?
| Activity | Immediate Predecessors | Time (Days) |
| A | ____ | 3 |
| B | A | 4 |
| C | A | 6 |
| D | B | 6 |
| E | B | 4 |
| F | C | 4 |
| G | D | 6 |
| H | E,F | 8 |