[All Steps] Given the estimated activity times and precedence below: Activity Optimistic Times (days) Most Likely Pessimistic Required Precedence A 6 7
Question: Given the estimated activity times and precedence below:
| Activity | Optimistic | Times (days) Most Likely | Pessimistic | Required Precedence |
| A | 6 | 7 | 14 | |
| B | 8 | 10 | 12 | |
| C | 2 | 3 | 4 | |
| D | 6 | 7 | 8 | A |
| E | 5 | 5.5 | 9 | B,C |
| F | 5 | 7 | 9 | B,C |
| G | 4 | 6 | 8 | D,E |
| H | 2.7 | 3 | 3.5 | F |
| What is the probability that the project will be completed within: | |
|
|
| b. 22 days? | |
| c. 25days? |
Price: $2.99
Solution: The downloadable solution consists of 3 pages