[Steps Shown] Eighty units of end item E are needed at the beginning of week 6 . Three cases (30 units per case) or J have been ordered and one case is
Question: Eighty units of end item \(\mathrm{E}\) are needed at the beginning of week 6 . Three cases ( 30 units per case) or J have been ordered and one case is scheduled to arrive in week 3 , one in week 4 , and one in week 5. Note: J must be ordered by the case, and \(B\) must be produced in multiples of 120 units. There are 60 units of \(\mathrm{B}\) and 20 units of \(\mathrm{J}\) now on hand. Lead times are two weeks each for \(\mathrm{E}\) and \(\mathrm{B}\), and one week for \(\mathrm{J}\).
- Prepare a material requirements plan for component \(\mathrm{J}\).
- Suppose that in week 4 the quantity of \(E\) needed is changed from 80 to 70 . The planned order releases through week 3 have all been executed. How many more Bs and Js will be on hand in week 6 ?
Deliverable: Word Document 